Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A 4 B 7 C 3 D B 10 E A, D 3 F C 6 G E, F 8 This exercise contains only parts b, c, and d. Part 2 b) The critical activities for the leadership training program development project are A - E - G B - D - E - G C - F - G .