Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:

Activity Immediate Predecessor(s) Time (days) A - 3 B - 7 C - 3 D B 10 E A, D 4 F C 5

G E, F 8

The critical activities for the leadership training program development project are: B-D-E-G

The project length for the leadership training program development project = 29 days

******WHAT IS THE SLACK TIME FOR ACTIVITY A****

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!