Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
Activity Immediate Predecessor(s) Time (days) A - 3 B - 7 C - 3 D B 10 E A, D 4 F C 5
G E, F 8
The critical activities for the leadership training program development project are: B-D-E-G
The project length for the leadership training program development project = 29 days
******WHAT IS THE SLACK TIME FOR ACTIVITY A****