Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity

activity immediate prececssor(s)

time days

a - 10
b - 6
c - 3
d b 2
e a,d 3
f c 5
g e,f 8

b. The critical activities for the leadership training program are either choice (1. c-f-g), (2. b-d-e-g), or (3. a-e-g)

c. The project length for the leadership training program development project is how many days

d. slack time for activites a-g

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!