Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity
| activity | immediate prececssor(s) | time days |
| a | - | 10 |
| b | - | 6 |
| c | - | 3 |
| d | b | 2 |
| e | a,d | 3 |
| f | c | 5 |
| g | e,f | 8 |
b. The critical activities for the leadership training program are either choice (1. c-f-g), (2. b-d-e-g), or (3. a-e-g)
c. The project length for the leadership training program development project is how many days
d. slack time for activites a-g