Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days)
A - 10
B - 6
C - 3
D B 2
E A,D 3
F C 5
G E,F 12
his exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are A-E-G C-F-G B-D-E-G
Step by Step Solution
There are 3 Steps involved in it