Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a
training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
This exercise contains only parts and
b The critical activities for the leadership training program development project are B D E G
c The project length for the leadership training program development project days.
d Slack time for each of the activities is: GIVE TIME FOR A THROUGH G