Question: A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?

A.

120

B.

220

C.

98

D.

112

E.

124