Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 5 C A 6 D B 3 E C D

Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 2 B A 5 C A 6 D B 3 E C D 9 F D 5 G F 3 H E G 6 b. What is the critical path? multiple choice 1 A-B-E-H A-C-E-H A-B-D-E-H A-C-E-F-G-H c. How many weeks will it take to complete the project? d. Which activities have slack, and how much? multiple choice 2 BPicture 3 weeksPicture DPicture 2 weeks. EPicture 2 weeksPicture HPicture 1 week. CPicture 2 weeksPicture FPicture 1 weekPicture GPicture 1 week

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!