Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B A 3 C A 5 D B 6 E C 7
| Schedule the following activities using CPM: |
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 4 | |
| B | A | 3 |
| C | A | 5 |
| D | B | 6 |
| E | C | 7 |
| F | D | 2 |
| G | E-F | 3 |
| H | G | 4 |
| Requirement 1: |
| What is the critical path? | |
| (Click to select) A-C-E-G-H A-C-D-F-G-H A-B-D-G-H A-B-D-F-G-H |
| Requirement 2: | |
| How many weeks will it take to complete the project? |
| Number of weeks |
| Requirement 3: |
| Which activities have slack? | |
| (Click to select) B-H-F B-C-F D-F-G B-D-F |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
