Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B A 3 C A 5 D B 6 E C 7

Schedule the following activities using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 4
B A 3
C A 5
D B 6
E C 7
F D 2
G E-F 3
H G 4

Requirement 1:
What is the critical path?
(Click to select) A-C-E-G-H A-C-D-F-G-H A-B-D-G-H A-B-D-F-G-H

Requirement 2:
How many weeks will it take to complete the project?

Number of weeks

Requirement 3:
Which activities have slack?
(Click to select) B-H-F B-C-F D-F-G B-D-F

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!