Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B A 3 C A 5 D B 6 E C%media:cm.png% D
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B A 3 C A 5 D B 6 E C%media:cm.png% D 7 F D 2 G F 3 H E%media:cm.png% G 4 What is the critical path? mu