Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B 3 6 D E F G H A A B C

Schedule the following activities using CPM:
Schedule the following activities using CPM:
Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B 3 6 D E F G H A A B C D D F EG N b. What is the critical path? A-C-E-G-H O A-C-E-F-G-H A-B-D-E-H A-B-D-F-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? C.10 weeks: E. 6 weeks. E. 3 weeks i H. 2 weeks. B. 2 weeks :D . 1 week