Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B A 3 C A 6 D B 7 E C D

Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A 4 B A 3 C A 6 D B 7 E C D 3 F D 5 G F 4 H E G 2 b. What is the critical path? multiple choice 1 A-C-E-F-G-H A-B-D-E-H A-C-E-G-H A-B-D-F-G-H c. How many weeks will it take to complete the project?