Question: Schedule the Following Activities using CPM: ID A B C A A 5 2 4 D B 3 4 1 1 E C,D F G
Schedule the Following Activities using CPM: ID A B C A A 5 2 4 D B 3 4 1 1 E C,D F G D F H Predecessor(s) E, G Time (Days) 2 Duration of the project is: 14 15 none 17