Question: Schedule the following activities using CPM NCTIVITY A B A D 2 5 6 3 9 5 3 6 media.co.png D D F G F

Schedule the following activities using CPM
Schedule the following activities using CPM
Schedule the following activities using CPM NCTIVITY A B A D 2 5 6 3 9 5 3 6 media.co.png D D F G F E media:cm.png b. What is the critical path? O ACE-H O A-B-E-H O A-C-E-F-G-H O A-B-D-E-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OE. 2 weeks: H. 1 week. OC. 2 weeks: F. 1 week: G. 1 week OB.3 weeks :D. 2 weeks