Consider the following project activities: Draw the AON and Use the Critical path method to compute the
Fantastic news! We've Found the answer you've been seeking!
Question:
Consider the following project activities:
- Draw the AON and Use the Critical path method to compute the CP, and total slack. [5]
- Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 30 days. [5]
Value of x : 1
Value of y : 4
Value of z : 5
Activity | predecessors | Optimistic | Most likely | Pessimistic |
A | - | 5 | 6 | 8 |
B | - | 3 | 4 | 5 |
C | A | 2 | 3 | 4 |
D | B | x-1 | x +4 | x+6 |
E | B | 1 | 3 | 4 |
F | - | 1 | 10 -z+x | 15-z+x |
G | E,F | 2 | 3 | 4 |
H | C,D | 2+y | 2+y | 2+y |
I | G, H | 3 | 4 | 5 |