Question: Consider the following project activities: Draw the AON and Use the Critical path method to compute the CP, and total slack. [5] Use PERT to

Consider the following project activities:

  • Draw the AON and Use the Critical path method to compute the CP, and total slack. [5]
  • Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 30 days. [5]

                      Value of x : 1 

                      Value of y : 4

                      Value of z : 5                                                            

Activity
predecessors
 
Optimistic
Most likely
Pessimistic
A
-
5
6
8
B
-
3
4
5
C
A
2
3
4
D
B
x-1
x +4
x+6
E
B
1
3
4
F
-
1
10 -z+x
15-z+x
G
E,F
2
3
4
H
C,D
2+y
2+y
2+y
I
G, H
3
4
5

 

Step by Step Solution

3.43 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Computer Engineering Questions!