Question: Suppose that the normal time for activity H is 9 weeks with a normal cost of $5,000. We can crash it to only 4 weeks
Suppose that the normal time for activity H is 9 weeks with a normal cost of $5,000. We can crash it to only 4 weeks with the crash cost of $10,000.
What will be the total activity cost if we crash it to 5 weeks ?
Group of answer choices
$9,000
$11,000
$5,000
$7,500