Question: Table 7.4 Activity Predecessor Time(weeks) A -- 8 B A 6 C -- 4 D C 9 E A 11 F B 3 G D,

Table 7.4 Activity Predecessor Time(weeks) A -- 8 B A 6 C -- 4 D C 9 E A 11 F B 3 G D, E, F 1 Using Table 7.4, what is the latest finish time for activity C? Group of answer choices week 4 week 10 week 8 week 6