Question: table [ [ , Start,Finish,Duration ( Days ) , ] , [ Activity , Node,Node,Optimistic,Most Likely,Pessimistic ] , [ A , 1 , 2

\table[[,Start,Finish,Duration (Days),],[Activity,Node,Node,Optimistic,Most Likely,Pessimistic],[A,1,2,41,50,59],[B,1,3,54,60,66],[C,2,4,58,70,82],[D,3,4,32,41,44]]
What is the estimated slack time for activity D?
0 days
19 days
20 days
79 days
80 days