Question: Tasks Duration (days) Dependency A 15 --- B 14 --- C 2 A, B D 1 B E 5 C, D F 1 D G

Tasks

Duration (days)

Dependency

A

15

---

B

14

---

C

2

A, B

D

1

B

E

5

C, D

F

1

D

G

15

C, F

H

8

E, G

I

12

B, H

J

35

C, G, H

K

25

H, I

L

3

H, J, K

Please draw a critical path network diagram and show the dummy activities clearly (with dotted lines), then determine the critical path(s).

Thank you.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!