Question: Tasks Duration (days) Dependency A 15 --- B 14 --- C 2 A, B D 1 B E 5 C, D F 1 D G
| Tasks | Duration (days) | Dependency |
| A | 15 | --- |
| B | 14 | --- |
| C | 2 | A, B |
| D | 1 | B |
| E | 5 | C, D |
| F | 1 | D |
| G | 15 | C, F |
| H | 8 | E, G |
| I | 12 | B, H |
| J | 35 | C, G, H |
| K | 25 | H, I |
| L | 3 | H, J, K |
Please draw a critical path network diagram and show the dummy activities clearly (with dotted lines), then determine the critical path(s).