Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 2 -- B 4 -- C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 2 | -- |
| B | 4 | -- |
| C | 1 | A,B |
| D | 6 | A,B |
| E | 3 | B,C,D |
| B-E; 7 | ||
| A-D-E; 11 | ||
| B-D-E; 13 | ||
| B-C-E; 8 | ||
| A-C-E; 6 |