Question: The critical path for the network activities shown below is __ with duration ___ Activity Duration Immediate Predecessors A 2 - B 4 - C

The critical path for the network activities shown below is __ with duration ___

Activity

Duration

Immediate Predecessors

A

2

-

B

4

-

C

1

A,B

D

6

A,B

E

3

B,C,D