Question: The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate A 10 --- B 8 --- C 2

The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate A 10 --- B 8 --- C 2 A D 4 A E 5 B,C,D

a.

none of the choices are correct

b.

A-D-E; 19 & A-B-D; 19

c.

B-E; 13

d.

A-D-E; 18

e.

A-B-C-D-E; 29