Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 10 -- B 8 -- C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 10 | -- |
| B | 8 | -- |
| C | 4 | A |
| D | 2 | A,B |
| E | 6 | D |
| ACDE; 22 | ||
| ACE; 20 | ||
| ABCDE: 30 | ||
| BE; 14 | ||
| ADE; 18 |