Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 --- B 6 A C
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 4 | --- |
| B | 6 | A |
| C | 7 | -- |
| D | 4 | A |
| E | 5 | B,C,D |
Group of answer choices
C-E; 12
A-B-E; 11
A-D-E; 13
A-B-C-D-E; 22
A-B-E; 15