Question: The critical path for the network activities shown below is _ with duration _. Activity Duration Intermediate predecessors A 4 - B 2 A C
The critical path for the network activities shown below is _ with duration _.
| Activity | Duration | Intermediate predecessors |
| A | 4 | - |
| B | 2 | A |
| C | 9 | - |
| D | 4 | A |
| E | 5 | B C D |