Question: The critical path for the network activities shown below is ________ with duration ________. Activity Duration Immediate Predecessors A 4 B 2 A C 9
The critical path for the network activities shown below is ________ with duration ________.
| Activity | Duration | Immediate Predecessors |
| A | 4 | |
| B | 2 | A |
| C | 9 | |
| D | 4 | A |
| E | 5 | B, C, D |
A.
A-B-D; 10
B.
C-E; 14
C.
A-B-E; 11
D.
A-B-C-D-E; 24
E.
A-D-E; 13
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
