Question: The critical path for the network activities shown below is_____ with duration ______. Activity Duration Immediate Predecessors A 10 --- B 8 --- C 2

The critical path for the network activities shown below is_____ with duration ______.

Activity

Duration

Immediate

Predecessors

A

10

---

B

8

---

C

2

A

D

4

A

E

5

B,C,D

A-C; 12
A-D-E; 19
B-E; 13
A-B-C-D-E; 29
none of the choices