Question: The critical path for the network activities shown below is_____ with duration ______. Activity Duration Immediate Predecessors A 10 --- B 8 --- C 2
The critical path for the network activities shown below is_____ with duration ______.
Activity | Duration | Immediate Predecessors |
A | 10 | --- |
B | 8 | --- |
C | 2 | A |
D | 4 | A |
E | 5 | B,C,D |
| A-C; 12 |
| A-D-E; 19 |
| B-E; 13 |
| A-B-C-D-E; 29 |
| none of the choices |
Step by Step Solution
There are 3 Steps involved in it
What constitutes a projects critical path is the ... View full answer
Get step-by-step solutions from verified subject matter experts
