Question: The expected activity time in PERT analysis is calculated as the sum of the activity variances, divided by six the simple average of the optimistic,

The expected activity time in PERT analysis is calculated as
the sum of the activity variances, divided by six
the simple average of the optimistic, pessimistic, and most likely times
the sum of the optimistic, pessimistic, and most likely times
the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b
the sum of the optimistic, pessimistic, and most likely times, divided by six

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!