Question: The expected activity time in PERT analysis is calculated as the sum of the activity variances, divided by six the simple average of the optimistic,
The expected activity time in PERT analysis is calculated as
the sum of the activity variances, divided by six
the simple average of the optimistic, pessimistic, and most likely times
the sum of the optimistic, pessimistic, and most likely times
the weighted average of a m and b with m weighted times as heavily as a and b
the sum of the optimistic, pessimistic, and most likely times, divided by six