Question: The expected activity time in PERT analysis is calculated as a . the simple average of the optimistic, pessimistic, and most likely times b .
The expected activity time in PERT analysis is calculated as
a the simple average of the optimistic, pessimistic, and most likely times
b the sum of the optimistic, pessimistic, and most likely times
c the weighted average of a m and b with m weighted times as heavily as a and b
d the sum of the optimistic, pessimistic, and most likely times, divided by six.
e the sum of the activity variances, divided by six.