Question: The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project. Task. Preceding Tasks A None B

The following table lists the tasks and preceding tasks for a project. Draw the activity-on-node diagram for this project.
Task………. Preceding Tasks
A………… None
B………… A
C………… B
D…………. B
E………….. C, D