Question: The snapback timing method in direct time study was used to obtain the times for an injection molding task. Only element d is a machine-controlled
The snapback timing method in direct time study was used to obtain the times for an injection molding task. Only element d is a machine-controlled element. a, b, c, and e elements are all external to machine-controlled element d, but f and g elements are internal. The machine allowance is 10%, and the PFD allowance is 15%. Determine
(a) the normal time for the cycle
(b) the standard time for the cycle
|
| Element | Description | Observed time (min) | Performance rating (%) |
|
| a | Worker load raw material into the hopper. (every 20 cycles) | 6 | 90% |
|
| b | Worker adjust the temperature and injection pressure. (every 10 cycles) | 2.5 | 90% |
|
| c | Worker starts the injection modeling machine. | 0.05 | 90% |
|
| d | Molten plastic is injected to the mold cavity and after solidification the part is ejected. | 1.1 | N/A |
|
| e | Worker removes the part and starts the machine again. | 0.1 | 90% |
|
| f | Worker separates runner and sprue from the part. | 0.03 | 90% |
|
| g | Worker deposits part in container and runner and sprue in scrap container. | 0.03 | 90% |
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts