Question: The table below is used for project scheduling: Activity Predecessor Duration, days A 5 B A 2 A 7 D B 00 8 E C

The table below is used for project scheduling:The table below is used for project scheduling:

The table below is used for project scheduling: Activity Predecessor Duration, days A 5 B A 2 A 7 D B 00 8 E C 9 F D 10 G F, E 11 What is the total project duration? o 21 days 32 days O 36 days o 25 days Question 40 What is the critical path? O A-C-E-G O A-C-E-F-G O A-B-E-G O A-B-D-F-G Question 41 Which activity/activities has/have the longest slack? OE OC & E O B&D