Question: The table below lists each work package with its duration and precedence description: Work package Duration Predecessors (daYS) 1.1 Demolition: remove all old appliances, 3


The table below lists each work package with its duration and precedence description: Work package Duration Predecessors (daYS) 1.1 Demolition: remove all old appliances, 3 None cabinets, and ooring 1.2 Demolition: haul away all materialsldebris 1 1.1 2.1 Order cabinets 2 1.2 2.2 Order sink/faucet 1 1.2 2.3 1.2 2.4 1.2 3.1 2.1&2.2&2.3 3.2 2.1 3.3 2.4 4.1 3.1 4.2 3.2841 4.3 4.2 4.4 4.3 4.5 3.3&4.4 5.1 4.5 6-1 5-1 6.2 Walk through I acceptance _ 6.1 _L