Question: Time Operator Machine Time period 0 . 5 Prepare mill for loading ( cleaning , oiling, and so on ) Idle 0 . 5 2

Time Operator Machine Time period
0.5 Prepare mill for loading (cleaning, oiling, and so on) Idle 0.5
2.25 Load mill Idle 1.75
4.5 Idle Mill operating (cutting material)2.25
5.25 Unload mill Idle 0.75
Idle time 2.253
Working time 32.25
Cycle time 5.255.25
Utilization rate 57%43%
Recommendations?