Question: Using EDD priority would result in what sequence for Jobs A, B, C, D, and E? Job Processing Time (days) Job due date (days) A
Using EDD priority would result in what sequence for Jobs A, B, C, D, and E?
| Job | Processing Time (days) | Job due date (days) |
| A | 20 | 180 |
| B | 30 | 200 |
| C | 10 | 175 |
| D | 16 | 230 |
| E | 18 | 210 |
Question 3 options:
| CABED | |
| CDEAB | |
| DEBAC | |
| ABCDE | |
| BAEDC |