Question: Using the information from the following table, create an AON network activity diagram: 1 the total duration of the project, 2 its early start, early
Using the information from the following table, create an AON network activity diagram:
1 the total duration of the project,
2 its early start, early finish, late start, and late finish times, and the slack for each activity (Use TE values)

Preceding Activities Activity Best Likely Worst A 12 15 25 B A 4 6 11 12 12 30 D 8 15 20 B, C A E 7 12 15 F E 9 9 U OWO I - - 42 19 G 13 17 D, E F H 5 10 15 G 11 13 20 2 3 6 G H J,1 K 8 12 22 Preceding Activities Activity Best Likely Worst A 12 15 25 B A 4 6 11 12 12 30 D 8 15 20 B, C A E 7 12 15 F E 9 9 U OWO I - - 42 19 G 13 17 D, E F H 5 10 15 G 11 13 20 2 3 6 G H J,1 K 8 12 22
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
