Question: Using the information from the following table, create an AON network activity diagram: 1 the total duration of the project, 2 its early start, early

Using the information from the following table, create an AON network activity diagram:

1 the total duration of the project,

2 its early start, early finish, late start, and late finish times, and the slack for each activity (Use TE values)

Using the information from the following table, create an AON network activity

Preceding Activities Activity Best Likely Worst A 12 15 25 B A 4 6 11 12 12 30 D 8 15 20 B, C A E 7 12 15 F E 9 9 U OWO I - - 42 19 G 13 17 D, E F H 5 10 15 G 11 13 20 2 3 6 G H J,1 K 8 12 22 Preceding Activities Activity Best Likely Worst A 12 15 25 B A 4 6 11 12 12 30 D 8 15 20 B, C A E 7 12 15 F E 9 9 U OWO I - - 42 19 G 13 17 D, E F H 5 10 15 G 11 13 20 2 3 6 G H J,1 K 8 12 22

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!