Question: Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project




Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way. Normal Crash Maximum Crash Time Normal Time Crash weeks Cost per Activity (weeks) Cost (55) (weeks) Cost (53) Reduced Week ($) A 3 500 2 900 1 400 B 4 600 3 700 1 100 C 6 800 3 1,325 3 17500 D 6 1,500 4 2,150 2 325 E 6 1,750 4 2,250 2 250 F 5 1,200 5 1,200 0 O G 7 1,500 5 1,820 2 160 H 3 500 3 500 0 0 Reduce G by v week(s), C by v week(s), at a cost of $ eTextbook and Media