Using the Network Diagram table below, complete the exercise as described in the steps: Steps 1. Sketch the network described in the table. 2. Determine the ES, LS, EF, LF, & slack of each activity 3. What is the critical path? Explain. (After completing this assignment, work with your team to add predecessor/successor relationships and duration to your Integrated Project plan) Network Diagram Task Predecessor Time A 4 B A 9 C A 11 D B 5 E B 3 F C 7 G DF 3 H E, G 2 K H 1