Question: WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000
| WBS Element | Planned Value (PV) | Earned Value (EV) | Actual Cost (AC) |
| 2.01 Airframe | 48000 | 48000 | 50000 |
| 2.02 Engines | 22000 | 21000 | 23000 |
| 2.03 Avionics | 80000 | 60000 | 45000 |
| 2.04 Communications | 30000 | 30000 | 30000 |
| 2.05 Tech. Manuals | 42000 | 42000 | 48000 |
| 2.06 Spares | 40000 | 35000 | 42000 |
| 2.07 Training | 80000 | 80000 | 86000 |
| Project Total | 342000 | 316000 | 324000 |
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX)
Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX?
| a. | The project is $26,000 under budget. | |
| b. | The project is $18,000 over budget. | |
| c. | The project is $8,000 over budget. | |
| d. | The project is on budget. |