Question: WBS Element Planned Value (PV) Earned Value (EV) Actual Cost (AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000

WBS Element

Planned Value (PV)

Earned Value (EV)

Actual Cost (AC)

2.01 Airframe

48000

48000

50000

2.02 Engines

22000

21000

23000

2.03 Avionics

80000

60000

45000

2.04 Communications

30000

30000

30000

2.05 Tech. Manuals

42000

42000

48000

2.06 Spares

40000

35000

42000

2.07 Training

80000

80000

86000

Project Total

342000

316000

324000

Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX)

Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project cost performance as of October 31, 20XX?

a.

The project is $26,000 under budget.

b.

The project is $18,000 over budget.

c.

The project is $8,000 over budget.

d.

The project is on budget.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!