Question: We are now part way through a project at a point where we had planned to have 49% of the work done. We have spent
We are now part way through a project at a point where we had planned to have 49% of the work done. We have spent $338,918 of the total budget of $717,944. We have completed 79% of the activities. What is the PV? What is the Schedule Variance?