Question: What is a quick way to find out which tasks have no resource assignments? a. Run a report from the Report Tab b. Look for
What is a quick way to find out which tasks have no resource assignments? a. Run a report from the Report Tab b. Look for unassigned resources on the network diagram c. View the Resource Usage sheet d. Activate the unassigned resources finder