Question: What is the earliest completion time for this project? A . 1 9 weeks B . 1 8 weeks C . 2 1 weeks D

What is the earliest completion time for this project?
A.
19 weeks
B.
18 weeks
C.
21 weeks
D.
20 weeks
.
.
.
Question content area right
Part 1
Activity
Predecessor
Time(weeks)
A
minusminus
8
B
A
6
C
minusminus
4
D
C
9
E
A
11
F
B
3
G
D,E,F
1