Question: What is the earliest completion time for this project? A . 1 9 weeks B . 1 8 weeks C . 2 1 weeks D
What is the earliest completion time for this project?
A
weeks
B
weeks
C
weeks
D
weeks
Question content area right
Part
Activity
Predecessor
Timeweeks
A
minusminus
B
A
C
minusminus
D
C
E
A
F
B
G
DEF