Question: What is the probability that the critical path for this project will be completed within 75 days? 80 days? 85 days? 90 days? Within what

What is the probability that the critical path for this project will be completed within 75 days? 80 days? 85 days? 90 days?
Within what amount of time is there a 90% probability that the critical path for this project will be completed? 95%? 99%?
Activity Start Finish Optimistic Most likely Most likely Pessimistic Te v o A 1 2 9 15 27 16 9 3 B 1 3 13 21 29 21 7.11 2.667 c 2 4 6 9 12 9 1 1 D 2 5 23 35 35 33 4 12 2 E 3 5 19 26 51 29 28.44 5.333 F 4 6 23 29 35 29 4 2 G 5 6 14 20 20 19 1 1 H 6 7 2 5 8 5 1 1 1 activity start finish te ES EF LS LF slack 1 2 16 0 16 1 17 1 B 1 3 21 0 21 0 21 0 2 4 9 16 25 31 40 15 D 2 5 33 16 49 17 50 1 E 3 5 29 21 50 21 50 0 F 4 6 29 25 54 40 69 15 G 5 6 19 50 69 50 69 O H 6 7 7 5 69 74 69 74 0Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts