Question: You have been asked to evaluate a project performance using earned value management techniques. Its currently day 54.24 of a project. BCWS, BCWP, and AC

You have been asked to evaluate a project performance using earned value management techniques. Its currently day 54.24 of a project. BCWS, BCWP, and AC to date are 24.04m, 23.68m and 22.43m respectively. Then what is the CV of the project to date? (Please keep two decimal points if applicable. Do not include unit "m"-million in your answers. For example, if your answer is 10m just write 10 not 10m)