Question: You have been asked to evaluate a project performance using earned value management techniques. It is currently day 53.35 of a project. BCWS, BCWP, and

You have been asked to evaluate a project performance using earned value management techniques. It is currently day 53.35 of a project. BCWS, BCWP, and AC to date are 20.6m, 23.82m, and 29.51m respectively. Then what is the CV of the project to date?

(Please keep two decimal points if applicable. Do not include unit "m"-million in your answers. For example, if your answer is 10 m, just write 10, not 10m or 10,000,000.)