Question: You have been asked to evaluate a project performance using earned value management techniques. It is currently day 55 of a project. BCWS, BCWP, and
You have been asked to evaluate a project performance using earned value management techniques. It is currently day 55 of a project. BCWS, BCWP, and AC to date are 22.6m, 21.3m, and 22.0m respectively. Then what is the CV of the project to date?