Question: You have been asked to evaluate a project performance using earned value management techniques. It is currently day 59.48 of a project. BCWS, BCWP, and
You have been asked to evaluate a project performance using earned value management techniques. It is currently day 59.48 of a project. BCWS, BCWP, and AC to date are 23.37m, 27.21m, and 21.92m respectively. Then what is the CV of the project to date?