Question: You have been asked to evaluate a project performance using earned value management techniques. It is currently day 56 of a project. BCWS, BCWP, and

You have been asked to evaluate a project performance using earned value management techniques. It is currently day 56 of a project. BCWS, BCWP, and AC to date are 26m, 29.6m, and 24.1m respectively. Then what is the CV in million dollars of the project to date? (Please keep two decimal points!)