Question: You have been asked to evaluate a project performance using earned value management techniques. It is currently day 59 of a project. BCWS, BCWP, and

You have been asked to evaluate a project performance using earned value management techniques. It is currently day 59 of a project. BCWS, BCWP, and AC to date are 22m, 26.2m, and 29.3m respectively. Then what is the CV of the project to date? (Please keep two decimal points. Do not include unit "m"-million in your answers. For example, if your answer is 10 m, just write 10, not 10m or 10,000,000.)