Question: You have been asked by a retail association to develop an inventory control pro-gram for use on a PC. The program development requires the completion
.png)
Using the Monte Carlo method, simulate 10 program development experiences. On the basis of your simulation results, what is the probability of finishing the project in 10 days?
Expected Time,Dvtion from Activity Description Days Expected Time, Days Probability +2 +1 0.1 0.2 0.3 0.4 A Write program Debug program Write user manual C
Step by Step Solution
3.44 Rating (163 Votes )
There are 3 Steps involved in it
Deviation days Program Realizatio n 1 2 3 4 5 6 in 2 1 0 1 7 8 9 10 R... View full answer