Question: Task C has two immediate followers, tasks D and E. Task D has a late start time of 10 days and task E has a
Task C has two immediate followers, tasks D and E. Task D has a late start time of 10 days and task E has a late start time of 8 days. Task C is 2 days long. What is the late start time of task C?